I need a clarifications regarding WIP caluclation for Internal order.

 

Our client use to run the WIP calculation for Internal order during month end. Even they use to run WIP for Internal order which doesn't have any actual cost for the month. As a result system is calculating calculated cost for finding the WIP for that month, even actual cost is not booked for that month in that internal order. So our client's requirement is that, system should not calculate WIP if Actual cost is zero for that month. But i saw system is caulcuating Calculated cost while running KKA1 which is almost equal to revenue of that month booked in the inernal order.

 

Few points to note:

 

1. Sale order is linked to internal order

2. Internal order is having revenue booked.

3. Actual cost not booked for the month

4. KKA1 is run to find the WIP(This client couldnt avoid since they have thousands of order during month end, unable to check each and every order)

5. WIP posting is done by using calculated cost caluclated by system during KKA1 run and settled to FI

6. Now system should not do WIP caculation if Actual cost is zero i.e. system should not calcaulted Calcualted cost if Actual cost is zero?

 

Kindly let me know if this approach is correct and provide us the soultion.

 